i'm trying implement my plan in bigGantt chart plugin by data entry (create task and sub-task manually).everything is fine but my problem is when add LAG value for any dependency link after a few hours value disappear and show me "0" number for LAG .
How can in fix this ?
Big gant version : 3.2.0-jira6
JIRA version : 6.4.9
Hi,
Please update to the latest version of the plugin as we have just fixed this bug.
We apologize for the inconvenience.