Remaining Estimate overshoots when edit LogWork

Ulisses Costa
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
May 24, 2022

Summary

If a user that logged too much time (and Remaining Estimate - RE - goes to 0) edits the logged time and reduce it (maybe he over reported time), the RE goes to the time he logged first time minus the time he adjusted to.

 

Example

Imagine I have a task that RE is 2h, just like the picture below:

Capture.PNG

When the user logs 2d (instead of 2h), the result is this one (as expected):

Capture2.PNG

 

Now the user realizes he logged too much time and he edits the LogWork entry from 2d (16h) to 2h, leaving the "Remaining Estimate" to "Adjust automatically", since he doe snot remembers how much time was actually in RE:

 

Capture3.PNG

 

The result is this:Capture4.PNG

 

A simple mistake done by a user when logs the time changes the scope of a sprint. Even worse: if the user is logging time for a previous day or week, when the adjustment of RE is made a big bump is seen in the previous day and a decrease in the current day, as can be seen here:

 

Capture5.PNG

 

Expected Behavior

When a user logs more time than it should and it edits (or deletes) that log entry and reduces the amount of time, when he selects the "adjust automatically RE", the RE shall be reduced and the maximum it shall be is the RE that according to the previous LogWork entry. If no other LogWork entry exists it shall goes to a maximum of the RE that was calculated in the beginning of the sprint.

0 answers

Suggest an answer

Log in or Sign up to answer
TAGS
atlassian, likes for trees, atlassian community, social impact, tree planting campaign, community kudos, atlassian giving, environmental impact, sustainability, likes for good, atlassian social responsibility, community challenge

Make every click count—help us plant 50,000 trees! 🌳

Want to make your everyday Community actions directly contribute to reforestation? The Atlassian Community can achieve this goal by liking a post, attending an ACE, sending your peers kudos, and so much more!

Help us plant more trees
AUG Leaders

Atlassian Community Events