I have 4 Stories in a sprint (in To Do) all showing this even if there are sub-tasks in alla of them. Why? The board filter only says: project = SMU and the Quick filter only has a selection of Epic Link (all correct showing)
Annoyingly, the epic link does not cascade down to sub-tasks, so if you use "Epic link = X" or even "Epic link is not empty", it will exclude the sub-tasks, as they don't have it.
I encountered a similar problem. Except it wasn't and Epic Link or Quick Filter related.
This would result in all story swimlanes being collapsed and all subtasks of the stories to read zero (just like the original post. Clearing my cache fixed the issue.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.