Hi All,
I am confused about how burn down and velocity charts work in JIRA.
We use hours for story points. So I understand the velocity and burn down are calculated as we close the stories.
So if the Time Tracking is on, does it calculate these even if the stories are not closed?
How are velocity/burn down values calculated?
Thanks.
Eshan
Basically, what is the relationship between story points and time tracking?
There is no relationship. Time tracking is a record of estimated time worked and actual. Story points are a measure of complexity.
A burndown chart can be told to use one of them (or another number) to track how you're doing.
Subtasks are irrelevant to burndown - they are a convenience for developers to break down a story, but can't be used for progress tracking.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Oi @Nic Brough -Adaptavist- aproveito a resposta que vc deu pra perguntar onde posso ver a config do restreamento do relatório do burndown? Onde trabalho dois cards nao aparecem mesmo finalizados....
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.