Story points, subtasks, burndown chart?

Eshan Salpadoru
Contributor
November 13, 2017

Hi All,

I am confused about how burn down and velocity charts work in JIRA. 

We use hours for story points. So I understand the velocity and burn down are calculated as we close the stories. 

So if the Time Tracking is on, does it calculate these even if the stories are not closed?

How are velocity/burn down values calculated?

Thanks.
Eshan

1 answer

1 accepted

1 vote
Answer accepted
Eshan Salpadoru
Contributor
November 13, 2017

Basically, what is the relationship between story points and time tracking?

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 13, 2017

There is no relationship.  Time tracking is a record of estimated time worked and actual.  Story points are a measure of complexity.

A burndown chart can be told to use one of them (or another number) to track how you're doing.

Subtasks are irrelevant to burndown - they are a convenience for developers to break down a story, but can't be used for progress tracking.

veudiniz May 10, 2022

Oi @Nic Brough -Adaptavist-  aproveito a resposta que vc deu pra perguntar onde posso ver a config do restreamento do relatório do burndown? Onde trabalho dois cards nao aparecem mesmo finalizados....