I'm unable to restore 2 sub-tasks that are children of an Active Parent issue. The restore button is missing. Any ideas? Again, the parent is active. We are on DC 9.5
Resolved this. sub-task was linked to multiple issues.
Usually, if you archive the Parent the Sub-tasks are also archived, and the same for restoring (hence why the button is not there).
If it's a single issue, could you archive the Parent, then restore it, and see if it restores the Sub-tasks at the same time?
Ste
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
No worries Jennifer!
Could you share how you fixed it, in case others have this issue again in future? :)
Ste
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
At the American Academy of Family Physicians, siloed marketing teams faced delays and duplicate work. Kerrie Gottschalk shook things up by moving the department to Jira, streamlining processes, boosting visibility, and sparking stronger collaboration.
Read the story
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.