Hi,
Velocity report in my project includes sprints from other projects.
The board filter used is configured only to display issues in that project. But the report includes sprint from other projects.
Please see the screenshot.
JIRA version : JIRA v7.6.6
Please let me know why is it happening like this and how to resolve the issue.
Thanks,
Krithica
Look at https://jira.atlassian.com/browse/JSWSERVER-13783
I think Scenario 2 is what you are facing
Hope that helps
I could see the issue is unresolved. How can i remove this empty sprint result from chart?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
From the same link "For Scenario 2, board admin may:
In this case, Sprint A doesn't contain anything related to Board B at all, but:
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
As in point 1. Reopen Sprint A from Board B's Sprint Report
I am unable to see the sprint from the board. The project contains only the sprints of the same project in sprint report drop down and not from the other project.
Only the velocity chart includes sprints from other project.
Please help.
Thanks,,
Krithica
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.