When selecting the “Sprint” as Start & Finish date, I would expect the visualization to take it over

chandra bhushan June 21, 2018

I wanted to use it to plan the upcoming work packages. When selecting the “Sprint” as Start & Finish date, I would expect the visualization to take it over.

But somehow this is only promoting the dates for artifacts being in the past or current Sprint. Which is bad, as I can’t have a visualization of the whole Epic (going over the future Sprint, maybe even PI).

 

Is there any option to activate to get this visualized?

4 answers

0 votes
Shunsuke Osawa June 25, 2018

Hi @chandra bhushan,

I would like to help you but couldn't figure out what exactly you want to do with it. It will be easier for us to understand if you could share the screenshots or something visual. 

Please feel free to create a support issue from our support portal if you want in private.

Cheers,

Sean, Ricksoft

0 votes
chandra bhushan June 24, 2018

Hi all,

I was using "wbs Gantt-chart for Jira plugins" in that is it possible to get entire epic visualization? as of now it was showing sprint planned on the view page in Gantt chart.

my requirement is to see entire epic on the view.please suggest me if it can be achieved using 

existing plugin which i am using now.

0 votes
Ollie Guan
Community Champion
June 21, 2018

Hi @chandra bhushan,

You can try this plug-in

BigGantt - neat gantt chart

chandra bhushan June 22, 2018

@Ollie Guan I was using "wbs Gantt-chart for Jira plugins" is it possible using this plugin to get the entire visualization of the whole Epic?

0 votes
chandra bhushan June 21, 2018

Gant-chart i forgot to mention which i wanted to use.