On my burndown chart, if I hover over some of the subtasks I see a negative value for Remaining Time Estimate. It looks like this:
*******************************************
FOD-219
Work logged
1h logged, Remaining Time Estimate changed from 4h to 3h
Remaining Time Estimate: -1h
*******************************************
I suspect it has to do with the way users are logging work. They are selecting an issue on the board and in the issue detail pane, they're editing the Remaining (Remaining Estimate) value. They're not using the Log Work window because that requires that they enter time spent on the issue and we're not interested in time spent. We're only interested in how much time is remaining.
Is using the Log Work window mandatory? If it is, having the Remaining Estimate field viewable and editable in the issue detail pane is inviting people to use it and cause more negative values so can it be removed?
Thanks
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.