I have a Agile Board setup and have an Epic created which has a Story which has 3 Subtasks. The three subtasks each had their Estimate and Remaining defined, but after I installed the sumUp Add-on the Estimated field for the Story still says unestimated.
I have gone through the sumUp Add-On configuration and added two rules: 1 to sum up the Original Estimate field and another to sum up the Remaining Estimate field.
Should the Story Estimate field have the sum of all of the Original Estimate fields from the subtasks?
Hello Mark,
this does not sound like a SumUp problem. SumUp calculate the sums in the issue navigator or in the Gadget Filter results if enabled.
To use the original estimate and remaining estimate you can change the Estimation calculation in the agile board configuration if it's a scrum board. Otherwise in the issue view you can enable the calculation of the estimaten to include the sub tasks.
Kind regards,
Benjamin
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.