Planned vs. Logged

Jo
Contributor
November 26, 2014

Hi

What is the ideal way to run a comparison between the planned and logged time and activities for a certain period of time for a team?

1 answer

0 votes
Susanne Götz [Tempo]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 27, 2014

Hi Jo,

You can view the planned and worked hours in the Team Timesheet, Report view. To show the Planned hours in this view, you need to add them by checking the "Planned" checkbox in the "Columns" dropdown. Please take a look at https://tempoplugin.jira.com/wiki/display/TEMPO/Report+View for more information.

Kind regards,

Susanne