Hi ,
recently upgraded Tempo, now my staff cannot plan work on weekend. Is there a new setting or is this a bug?
I am using Version Tempo Timesheets - 7.9.1.3, with JIRA Version 6.2.5.
Hi Grace,
This is a known regression in Tempo 7.9.
We are aware of the problem and are evaluating how we can remedy this problem going forward.
Please watch https://tempoplugin.jira.com/browse/TT-823for further updates.
Sorry for the inconvenience.
Regards,
Benedikt
HI there,
This is what i did:
1. Go to Tempo select Timesheet
2. Click Plan Time. The Plan Time dialog box popup.
3. Select a weekend e.g. 5 July 2014, select an issue, enter hour. click Plan Time button. Plan Time dialog box closed.
4. The plan time is not displayed in the timesheet.
No error meesge.
Regards,
Grace.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Grace,
Sorry for your inconvenience, I have not been able to recreate this problem. It might be good to follow up on this problem in our support system. Can you create a ticket in our Tempo support project (https://tempoplugin.jira.com/browse/JTS) and give us some more information about this problem.
Are all users affected by this, does it happen when planning on Issue level or versions, components. Do you get any error messages. Screenshots might help us to investigate this.
Kind regards,
Susanne
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.