Hi,
I have a few problems with epics in Tempo Planner.
For one, I can´t change the status of an epic in the program board, I can drag it but after a refresh the change is gone.
The other problem is with the epics in the team backlog view. There I don´t have the different sections for the epics, idea, todo, in progress, done. How can I get them? Plz check the screen, it looks not quite what I expected, I expected the issues of the epic there:
http://i.imgur.com/eLJyxct.png
Thanks a lot!
Greetings
Marc
Hi Marc,
in the Team Backlog, only Epics that are linked to the Team with the Team Custom field (see https://tempoplugin.jira.com/wiki/display/PLANNER034/Organising+epics for more information). Regarding the grouping, this is done by using the Epic status (a JIRA configuration, please see also https://confluence.atlassian.com/jirasoftwareserver071/working-with-epics-800706692.html)
These statuses are also used in the Program Board.
Regards,
Susanne
I think I have a problem there, I have None, Aufgaben, In Arbeit, Fertig. They don´t seem to fit the standard and that´s why they don´t "save" the drag.
Any ideas?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Renaming the status in the database worked. You shouldn´t rely on the english names there.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.