×Hi,
I have a few problems with epics in Tempo Planner.
For one, I can´t change the status of an epic in the program board, I can drag it but after a refresh the change is gone.
The other problem is with the epics in the team backlog view. There I don´t have the different sections for the epics, idea, todo, in progress, done. How can I get them? Plz check the screen, it looks not quite what I expected, I expected the issues of the epic there:
http://i.imgur.com/eLJyxct.png
Thanks a lot!
Greetings
Marc
Hi Marc,
in the Team Backlog, only Epics that are linked to the Team with the Team Custom field (see https://tempoplugin.jira.com/wiki/display/PLANNER034/Organising+epics for more information). Regarding the grouping, this is done by using the Epic status (a JIRA configuration, please see also https://confluence.atlassian.com/jirasoftwareserver071/working-with-epics-800706692.html)
These statuses are also used in the Program Board.
Regards,
Susanne
I think I have a problem there, I have None, Aufgaben, In Arbeit, Fertig. They don´t seem to fit the standard and that´s why they don´t "save" the drag.
Any ideas?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Renaming the status in the database worked. You shouldn´t rely on the english names there.