I am using Jira Structure with Gantt and trying to schedule tickets on the project with resource levelling.
Levelling priority in Gantt config is "1/index*100000".
For some tasks, Structure performs levelling correctly, but for some...
The delayed task has no relations with other tasks. I cannot find any reason why it can be delayed.
So, my questions are:
Hi Yuri!
I'm Alexey from ALM Works.
Unfortunately it is not possible to tell what is wrong in your case without WBS and Resource Allocation also visible.
One thing I can suggest is to try to "Clear existing leveling delays" by selecting corresponding checkbox (leveling delays are summed up each run so clearing them could help):
By the way, although your formula looks correct, since Structure.Gantt 2.4 there is a special "Structure Index" attribute available for Leveling by task index:
Best regards,
Alexey
ALM Works
Thanks, Alexey.
I had no this checkbox, because of the very old Structure version. After updating and selecting it, everything works fine.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Yuri, glad to hear that!
Alexey,
ALM Works
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.