When I got to view all Gantts in WBS Gantt for Jira I copy a project and rename it from "ABC" to "DCE". When I make a change in "DCE" like assignee it also changes in project "ABC". How do I clone project "ABC" and rename it to project "DCE" so it is a stand alone project. Thank you
Hello @Tony San Nicolas
My name is Álisson, I'm from Ricksoft team and I would like to help you with this question.
When an assignee is changed for an issue at WBS Gantt-Chart, the Jira's assignee for the issue is updated also. For this reason, we do not recommend an issue to be managed at multiple Gantts.
Please let me know if there are any doubts.
Best regards,
Álisson
@Tony San Nicolas, did @Álisson Dalmago comment help you out?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I have the same problem, Whenever I change or update the issue in "DCE" it gets changed in "ABC". How can I make those projects work
separate?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello @[deleted] ,
This is Hikaru from Ricksoft.
Are these issues in "DCE" and "ABC" the same issues (Meaning they have the same issue keys)? If so, you are just editing the same issue from different WBS Gantt -Charts.
When you copy WBS Gantt-Chart, it DOES NOT copy the issues in the Gantt-Chart. It just copies the Gantt configuration.
Therefore, you need to clone the Jira project first, and then create WBS Gantt-Chart from the project to make it work. You can create a Gantt scheme to share the Gantt Configuration as well.
Cloning a Jira project with all its issues is not an easy task. There are some community posts that you can refer to.
Best,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Recommended Learning For You
Level up your skills with Atlassian learning
Redesign your workweek
Configure your calendar to prioritize high-impact work and goals. You'll learn how to set daily priorities, prioritize essential meetings, and schedule focus time.
How to run effective meetings
Lead efficient meetings that have clear goals, keep your attendees actively engaged, and use the Atlassian Playbook to improve meeting success.
How to build strategic guidance
Build a high-performing, effective team by providing clarity, defining success, and making it clear who will benefit from your efforts — a technique we call strategic guidance.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.