Hi, I'm trying to use the due date and mark complete to indicate the specified date in the "Due Date" field is the actual completion date. The search parameters I have seen searching on Due Date is for searching for cards due in the next day, 7 days. Is it possible to specify a previous date range for me to look at what cards where completed in the month of January, for example?
Thanks,
WInnie
Hi Winnie,
try this.
due >= 2018-01-01 AND due <= 2018-01-31