Why are Rolled-up Estimates not the same as the Remaining Hours shown in Progress (hours)?
I read from here https://support.atlassian.com/jira-software-cloud/docs/track-progress-using-estimates-in-advanced-roadmaps/ that values may be inconsistent between rolled-up estimates and progress bar hours. But why is that? And in this case, which will be more accurate?
Hi @Lena Boiser
on the Jira Data Center documentation it seems to me a bit more clearly.
From my point of view it can be due to unestimated issues:
Any unestimated issues may impact the accuracy of your progress. If you've enabled rolled-up values in a plan, you may see inconsistent values between rolled-up estimates of a parent issue and the values in the progress bar.
Which value is more accurate I'd suggest to test out on a few plans. It should show clearly when comparing a few plans.
Cheers,
Daniel
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.