Hi all
Is there an elegant way to allocate specific time to a task per day in Tempo Planner
Scenario
A PM has created a task called Review Technical Scope and Assigned it to a resource with and estimate of 10 Hours in a 5 day week in JIRA and it is synched with Tempo Planner
Tempo planner will automatically spread the 10 hours across 5 days = 2 hours per day
What i want to do is phase the effort across the 5 days e.g
I can split the task into 5 and allocated each segment the effort but i find this very cumbersome to do particularly for tasks which take longer
Any ideas welcome
Perhaps a feature change could be introduced that can model the daily distribution of hours at creation without the need to split tasks
Hi @Rakesh Pradhan , thanks for your question.
I don't know that this is possible yet in Tempo, but BigPicture has a function like this called, 'workload contouring' - https://appfire.atlassian.net/wiki/spaces/DLP/pages/297046379/Workload+contouring
^ Is this more what you are after?
Thanks Valerie
We have big picture and have seen the workload contouring feature . We are trying to use Tempo capacity planner add in to manage resource assignment and allocation as we already have tempo timesheets as our time tracking tool