Internet usage on Confluence Migration

SaravanaKumar
Contributor
November 21, 2022

If I have a space of 30 GB when migration, do we need 30 GB of internet data, or is the internet just required to connect the server to the cloud?

1 answer

1 accepted

2 votes
Answer accepted
Alexis Robert
Community Champion
November 21, 2022

Hi @SaravanaKumar , 

 

if you're talking about the Confluence Cloud Migration Assistant, and that it's giving you the information about 30GB of attachment to migrate : you will need to use 30GB of internet data to transfer the data between Confluence on-premise and Confluence Cloud.

 

Let me know if this helps, 

 

--Alexis