Can I configure Time Stamp field in a team-managed JSM project to have only Business hours available

Claudia Riverin
Contributor
March 28, 2025

Hi! is it possible to have only business hours available in the time stamp field in a JSM team-managed project? 

 

Thanks!

 

Capture d’écran, le 2025-03-28 à 09.11.07.png

2 answers

2 accepted

5 votes
Answer accepted
Luis Andino Rodriguez
Contributor
March 28, 2025

Unfortunately, you cannot restrict the Time Stamp field in Team Management Project. Team Managed Project has limitations on Field configurations.

Claudia Riverin
Contributor
March 28, 2025

So sad. 

Thanks for the answer Luis ;) 

1 vote
Answer accepted
Claudia Riverin
Contributor
March 28, 2025

Capture d’écran, le 2025-03-28 à 09.11.07.png