How do I count remaining working days in a year from eazyBI?

Cyber Tech Group July 4, 2023

I'm doing a forecast report to see if we can finish all remaining issues in Jira.

1 answer

1 accepted

3 votes
Answer accepted
Martins Vanags -eazyBI-
Atlassian Partner
July 4, 2023

@Cyber Tech Group 

Try creating new calculated measure using this formula:

DateDiffWorkdays(
'today',
DateAdddays('first day of next year',-1)
)

It should count workdays between today and the end of this year

You can search for great calculation examples in eazyBI documentation page and community platform

 

Martins / eazyBI

Cyber Tech Group July 4, 2023

Awesome! Just what I'm looking for! Thank you!