Hi everyone,
Is it possible to automatically capture the date when the status of an issue in a project changes, such as from "TO DO" to the "Planning" phase, and then store this date in a custom field?
I would like to have it for the whole path for the issue, maybe some of you guys know how to do it :)
Best regards,
Vladimir
Hi, Vladimir! How are you?!
Yes, it is possible. You need set a value on field that you neet copy the date. And you can do this on Automation. (I used Due date)
To manipulate the date with something, you can use date smart values. Like that:
Hope this helped you!
Roberto Miasack
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Show up and give back by attending an Atlassian Community Event: we’ll donate $10 for every event attendee in March!
Join an Atlassian Community Event!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.