Our upper management team has asked for a couple reports and I need some guidance.
Backlog Progress
They are wanting to make sure a specific team is making progress on backlog items. Any suggestions on this? Our backlog is constantly changing, so I'm finding it slightly difficult to determine how to accomplish this.
Version Updates/Rollovers
We have a team working off of a kanban board that sets work up similar to sprints, but by using the version field to setup sprints. Is there a way to see what issues are worked on across multiple versions?
Thank you!
Backlog progress
IMO, assuming all issues start in the Backlog, the Created vs. Resolved chart does a good job of illustrating if the team is keeping up with the incoming demand. It allows you to trend progress over time the idea here is to make sure that the team is not falling behind, which would equate to a growing backlog.
not sure what to suggest for the second request.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.