Tien Nguyen February 23, 2022

Can I apply the workflow with 5 statuses for the scrum board only got 3 columns To Do - In Progress - Done. I've tried to create a workflow for the tasks, and it changes the board. If I could, how could I do that?

Thanks

1 answer

1 accepted

0 votes
Answer accepted
Emily Chan
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
February 23, 2022

Hi @Tien Nguyen 

Do you mean mapping each of the 5 statuses of either one of the columns To Do/In Progress/Done? 

If so, (assuming you're using a Team Managed Project, which you can check in the bottom left corner of your project), these tutorials might answer your question:

It works differently if you're using Company Managed Projects, then the solution would be different. Let me know if this is the case :) 

Tien Nguyen March 5, 2022

Well, I think it's not what I'm finding. Anyways, it's beneficial for my next project. Thank you so much