Add a non-working day in Burndown Chart

Jorge_de_Carlos
Contributor
October 15, 2018

Hi everyone,

We want to reflect a non-working day in Burndown Chart. Last Friday (October, 12) was free day in Spain but obviously, Jira didn't reflect It in the graphyc.

Could someone please help us? We want to reflect it to reports.

Thank youerrorjira1.png

 

1 answer

1 accepted

1 vote
Answer accepted
Thomas Schlegel
Community Champion
October 15, 2018

Hi @Jorge_de_Carlos,

you can set non-working days in your board configuration under "Working Days":

image.png

Jorge_de_Carlos
Contributor
October 15, 2018

Thank you very much @Thomas Schlegel!

Thomas Schlegel
Community Champion
October 15, 2018

You're welcome, @Jorge_de_Carlos

TJ Smith
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
July 2, 2019

@Thomas Schlegel I added a non-working day after a sprint had already started.  Should I expect to see it appear in Burndown Chart? It is not displaying as I anticipated.

Thomas Schlegel
Community Champion
July 2, 2019

Hi @TJ_Smith

I just tested this in my playground project and yes, if I add more non-working-days after the sprint started, you can see them greyed out in the burndown chart:

Before: 

image.png

 

After adding the days:

image.png

TJ Smith
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
July 2, 2019

@Thomas Schlegel thanks for confirming.  After deeper investigation, the problem has been resolved...

 

PEBKAC.png

Thomas Schlegel
Community Champion
July 2, 2019

Great, you found the problem, @TJ_Smith  