After creating a new program in Big Picture, some of the new created tickets are not shown properly in Gantt.
I've created Epic's and in the epic's and new tasks within the Epic. But now, some of the Epic's are displayed as a part of the previous Epic.
I've attached an example showing the issue I encounter:
1.5 is an Epic with serveral tasks
1.6 is now a part of Epic 1.5. How can I change this to look like 1.5. and 1.7 ?
Dear Team,
Can someone please let me know due to Big Picture plugin Is JIRA application getting down?
Regards,
Nirmalya
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Please select the epic which you want to make a parent in Gant chart and then click on the arrow on top <---
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.