Tineke Huizinga October 29, 2018

From a simplicity point of view, let us not waiste manually recalulation how many days spent instead of hours. So my question is how to show the burndown chart in days instead of hours. 

1 answer

0 votes
kavi shree
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 29, 2018

Hi Tineke,

Simple way is log the work in days rather then hours/mins. Burn-down chart will get reflected in days.

Tineke Huizinga October 29, 2018

Strange because that is what we do already. 