After starting the sprint, the only event that I can see in the burndown is the one "Sprint start", it doesn't matter if I log work, close issues, open issues, change scope... Burndown doesn't reflect any of those changes. Am I missing something? Does it need time to refresh by itself? Is configured to track Time.
Thanks for your comments
Thanks Sateesh, the status of the issues are Resolved, work log done, if I look into the Issue detailes I can see clearly the remaining estimate, the logged time, everything... Is just all this information is not shown on the burndown chart
Also check the board for what issue statuses are in To Do , In Progress , Done etc.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for your quick answer, actually I've been doing all those things in previous sprints but right now at the current, the burndown suddenly stopped tracking and showing changes, I know is weird, that's why I write here. For testing I have just create a new user story in the sprint which obviously will take a huge scope change and the chart keeps like nothing. I'm so confused, I don't know where else to check.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Could you please check the board configuration at Board --> Configure board --> Estimations and share ? Unfortunately , burn down will only be reflected at the time of story closure / resolution time.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Also please check if there are any parallel sprints for the same project on a different agile board ?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Firstly , please check whether the sprint is selected properly at the report.
For close and open issues, Scope change and story points / time spent you can refer burn down charts.
Logged work will be reflected as cumulatively at time spent when the issue is closed.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Join us to learn how your team can stay fully engaged in meetings without worrying about writing everything down. Dive into Loom's newest feature, Loom AI for meetings, which automatically takes notes and tracks action items.
Register today!Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.