Can I customize status on which rollover report is based?

Kaitlyn Luboff March 18, 2022

We do our sprints a little differently than most, where a story just needs to finish QA and Owner Acceptance by the end of the sprint, and it isn't marked "Done" until closer to release (which may be several days after the sprint ends).

Because of this, our rollover count is much higher than we would expect.

Is it possible to customize the rollover sprint report, such that we're calculating rollover based on number of stories that have made it to OA (or whatever status we choose) by sprint end, rather than the number of stories that have reached "Done" status?

1 answer

0 votes
Ste Wright
Community Champion
March 19, 2022 edited

Hi @Kaitlyn Luboff 

Is changing the Definition of Done in the board an option?

Scrum Boards don't work off the last status in a Workflow, just what status(es) are in the most right-hand column.

This means you could...

  • Go to Board Settings > Columns
  • Remove the Done status from the board
  • Set the last column (with a green band) to contain Owner Acceptance

^ Then, Jira would class an Issue as completed in a sprint if it reached that status instead, and not roll the data over to the next sprint.

The end-to-end flow of the data could then be tracked elsewhere, such as in the release hub or in another board.

Ste

Suggest an answer

Log in or Sign up to answer
TAGS
atlassian, out of office, loom, confluence, async collaboration, meeting recaps, remote teamwork, team alignment, knowledge sharing, AI-powered notes, productivity tools, workforce continuity, teamwork collection

Put your meeting notes on autopilot with Loom + Confluence

AI-powered meeting notes keep work moving even if you’re out of the office. Enjoy your well-deserved time off and return refreshed, confident you’ll catch up in no time.

Learn more
AUG Leaders

Atlassian Community Events