Hi,
Can I make original estimate field as non mandatory field for standard issue types.
I want it mandatory only for sub tasks.
Hi @Asha ,
To make original estimate field Mandatory only for subtask you can follow the below steps:-
Now when you create any subtask in that project the "Original Estimate" field will be mandatory and other standard issue types will follow the default field configuration.
Thanks & Regards,
Mayuresh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.