Jira Data Center 9.0.0: I am trying to change the default value for Priority which currently defaults to 3- Medium.
I am looking at the "Edit priority scheme" window of my priority scheme which is noted as USED BY 2 PROJECTS, the two I have thus far. I changed the Default priority to None and click the Update button. I go to create an issue in those two projects but they still default to a priority of 3 - Medium.
I re-indexed but still they do not default to None.
I logged out and back in but still they do not default to None.
Is there something else to set or associate? Just wondering what I am missing.
Hi @Boyd K
Actually it's not woring, it take the middle priority, if you have 5, it will take the 3rd.
Related to this reauest I think.
https://jira.atlassian.com/browse/JRASERVER-13048
Regards
Yeah! that's true. It takes the middle value as default.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.