Days Remaining Error !!!!!!!!!!!!!! GreenHopper

haitham ahmed March 24, 2012

- Time Tracking

Time Tracking is currently ON.
The number of working hours per day is 9.
The number of working days per week is 5.

- General Configuration >> Non Working Days

  • 23/Mar/12Delete
  • 24/Mar/12Delete
  • 30/Mar/12Delete
  • 31/Mar/12Delete
  • 6/Apr/12Delete
  • 7/Apr/12Delete

*************************************

GreenHopper Days Remaining at dashboard

(9) Days Remaining

Our spirnt information at Agile [Manage your dashboard with GreenHopper] >> Planning Board
Parent: 1.19
Start Date: 20/Mar/12
End Date: 9/Apr/12
Release Date: 9/Apr/12
Please how can it get this number [9] ? the number must be [13] days not [9] ???????

2 answers

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 25, 2012

I'm not sure that my logic matches what Jira is doing, but I get 9 days too

Your sprint is set to cover three weeks, as below. My x's represent the days you've said "non working day", and the numbers are a counter.

20 Mar  Tue  1
21 Mar  Wed  2
22 Mar  Thu  3
23 Mar  Fri  non-working
24 Mar  Sat  non-working
25 Mar  Sun  4
26 Mar  Mon  5

27 Mar  Tue  6
28 Mar  Wed  7
29 Mar  Thu  8
30 Mar  Fri  non-working
31 Mar  Sat  non-working
 1 Apr  Sun  9
 2 Apr  Mon 10
3 Apr  Tue 11
 4 Apr  Wed 12
 5 Apr  Thu 13
 6 Apr  Fri  non-working
 7 Apr  Sat  non-working
 8 Apr  Sun 14
 9 Apr  Mon  15 Release

By my counting, you should therefore get 15 days.

However, your time-tracking says there are only 5 working days per week, so you need to remove 2 days per working week, which means you get 15 -6 = 9 days...

haitham ahmed March 25, 2012

Thanks for your reply but

20 [1], 21[2], 22 [3], 25 [4], 26 [5], 27 [6], 28 [7], 29 [8], 1 [9], 2 [10], 3 [11], 4 [12], 5 [13], 8 [14], 9 [15]

20 [15], 21[14], 22 [13], 25 [12], 26 [11], 27 [10], 28 [9], 29 [8], 1 [7], 2 [6], 3 [5], 4 [4], 5 [3], 8 [2], 9 [1]

Although non wroking days calculated before 6 days

Today 26 / 3 / 2012 >>>> The counter on dashboard now {8} , the counter must be 26 [11] 11 Days

If you have answer for this issue please reply me

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 25, 2012

I'm sorry, my formatting got all messed up when I posted the original. I've re-done it as a code block, which seems more clear.

I don't understand what you're asking now though. What I'm trying to point out is that you have told Jira that your sprint is 21 days long, with 6 non-working days, and 5 working days per week (i.e. 2 in 7 are also non-working). 21 - 6 - (3 * 2) = 9 days. Whatever order you do the two "2 days not working", you get 9 working days in the three weeks.

haitham ahmed March 25, 2012

Our Sprint is 15 days without non working days

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 25, 2012

Yes, I understand that, but you've added a load of non-working days to that particular sprint, so it's cutting it down more.

You've got 21 days listed

You have set your working week to 5 days, which means you need to remove 2 in every 7 days, which, for 3 weeks, means 6 to remove.

You've set up non-working days = 6, so you need to subtract them.

That leaves 9 working days.



haitham ahmed March 25, 2012

The number of working hours per day is 9.
The number of working days per week is 5.

2 non- working days + 5 working days = total 7 days our sprint 21 days = 3 weeks that's right ok until now

we start sprint 20/03/2012 and it ends 09/04/2012 we cancel 2 non- working days for every week so non- working days will be 6 days

20/3 [15], 21/3 [14], 22/3 [13], 25/3 [12], 26/3 [11], 27/3 [10], 28/3 [9], 29/3 [8], 1/4 [7], 2/4 [6], 3/4 [5], 4/4 [4], 5/4 [3], 8/4 [2], 9/4 [1]

Today 26 / 3 / 2012 >>>> The counter on dashboard now {8 Days Remaining} , the counter must be 26/3 [11 Days Remaining ]

How can change this number from 8 to 11?

Thanks for your replies and effort with me

I got the reason we calculated non-working days twice the one time in General Configuration under GreenHopper, the second time in General Configuration on project's level How can i remove non-working days in General Configuration on project's level , Jira replys

GreenHopper includes global non-working days, they can be modified below to meet specific project requirements. Note: Global non-working days can be modified by your JIRA Administrator. These dates will not be shown in your charts. All worklogs will be associated to the previous working day.

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 25, 2012

I don't understand what the confusion is - based on what you've got in Jira/Greenhopper, it's doing the right calculation, and I don't get why you keep saying it's wrong. It's probably me just not being able to grasp what I'm reading - could you explain why you are expecting non-working days to be included as working days?

You've got 5 working days per week.

Then you've got global non-working days (which you hadn't mentioned before),

Then you've duplicated that at a project level.

You need to remove the duplicated days to begin with (project administration level), and then talk to your admins about the global non-working days, as it sounds like they might be wrong.

haitham ahmed March 25, 2012

I got it , i was supposed to change the number of working days per week from 5 to 7 in time tracking.

Many thanks for your replies and effort with me

0 votes
Jakub Pierzchała
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 25, 2012

Hmm lets see, from my count:

1 - March 26th
2 - March 27th
3 - March 28th
4 - MArch 29th
5 - April 2nd (March 30th is a non working day)
6 - April 3rd
7 - April 4th
8 - April 5th
9 - April 9th (Release date, April 6th is a non working day)

Sums to 9 days, The bigger question is how did you get 13 :)

Suggest an answer

Log in or Sign up to answer
TAGS
atlassian, team '25 europe, atlassian event, barcelona 2025, jira, confluence, atlassian intelligence, rovo, ai-powered collaboration, developer tools, agile teams, digital transformation, teamwork solutions, atlassian conference, product announcements

🌆 Team '25 Europe registration is now open!

Join the largest European gathering of the Atlassian Community and reimagine what’s possible when great teams and transformative technology come together. Plus, grab your Super Fan ticket now and save over €1,000 on your pass before prices rise on 3 June.

Register now
AUG Leaders

Atlassian Community Events