May 30, 2017

So i am slowly implementing Agile Methodolgy in to my organization.

I have written Epics and Stories using the "As a <user> I want <something> So that <rationale>" standard and have assigned Story Points to each Story. 

I have also started to get the dev team to log time spent on each Issue. 

However, I still cannot produce Velocity Report. Is there something else i need to do?

1 answer

1 vote
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
May 30, 2017

A velocity report is generated by the boards you're working on, so you need to go to the boards to get there.

But, it's not really calcuable with any accuracy until you've done a few sprints - from memory, you'll need to complete three sprints before it will give you full details.

Vincent Lyon
Contributor
May 30, 2017

Hi Ben,

To complete what Nic said :

Velocity Chart

This link leads to the JIRA documentation about Velocity Chart. This chart is available in Report Mode.

Note that it won't display the current sprint, so as Nic said, you'll need to complete a few sprints before.