I am comparing the burndown and the burnup charts for our current sprint.
When I examine our sprint board, we have 116 points in the sprint today, and we have 32 points remaining to complete
The burndown chart is showing that our peak total scope was 116, and shows 32 points remaining.
The burnup chart is showing 140 points scope, and 87pts completed. We had some tickets erroneously added to our sprint, but we since removed those.
I would assume that if we accidentally added 24 points, but then removed those 24 points, they would be removed from the burnup graph?
Am I doing something wrong? Am I misunderstanding how this works? Is this a bug?
Join us June 26, 11am PT for a webinar with Atlassian Champion Robert Hean & Loom’s Brittany Soinski. Hear tips, stories, and get your burning questions answered. Learn how Loom makes training and enablement easier. Don’t miss it!
Register todayOnline forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.