I am working with 3 teams who are have multiple active Sprints at the same time. However, I don't think they need this because although the teams share the same backlog, I think all they need are their own Boards configured separately. In that way they can then at least capture the velocity of each team. Also it has led to a practice of not closing off Sprints. As far as I can tell Parallel Active Sprints are only useful if one team is working on multipleSprints.
So I want to unwind and configure individual Board for the teams to create their own Sprints off the same Product Backlog. However, I am not sure whether the Parallel Active Sprint option that I want to undo works at System, Project or Board level.
If it works at Project level as I suspect - has anybody got a strategy for mving back to having separate boards that will have least disruption.
Regards
Hi Ian,
Parallel sprints are configured on a site wide basis. You can find the setting for this in Jira Server by going to Settings (Cog Icon) -> Applications -> Jira Software Configuration. There is a checkbox here that will allow you to enable parallel sprints for the entire site.
There is a feature request to allow administrators to manage this feature on a per board or per project basis over in https://jira.atlassian.com/browse/JSWSERVER-12588
However so far, there does not seem to be any alternative work-around for selectively using this feature.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.