×I have been looking at creating plans in Jira for our development teams on the basis of giving us a solid holistic view of epics in progress and capacity etc.
I have configured two plans and on one of the plans for some reason it keeps showing as unassigned (see below).
I cant work out why these (total of around 5 epics appear in this section, they are assigned to a team and on most I am assigned to them as Assignee but yet they still appear in this section.
Also have tried changing the plan to look at a project or the teams board but still they appear there.
Any assistance greatly appreciated.
Hi @James Doyle
You probably already found the solution, but then this might help others having the same issue:
Solution can be found in this article: https://community.atlassian.com/t5/Advanced-planning-questions/Unassigned-in-Advanced-Roadmap/qaq-p/1857975
Once all child issues under an epic have been assigned to a team, the epic disappears from the Unassigned section.
Hope this helps.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @James Doyle
I think the unassigned means unassigned to a specific user, but not a team. If you assign it to a user, it should disappear from Unassigned group.
Thanks,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Atlassian Government Cloud has achieved FedRAMP Authorization at the Moderate level! Join our webinar to learn how you can accelerate mission success and move work forward faster in cloud, all while ensuring your critical data is secure.
Register Now
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.