I have an automation that runs every 2 weeks to create a sprint that starts 4 weeks from now so that the backlog always has 2 future sprints in it. I want to put in the sprint name the start and end dates for the sprint. So if the sprint starts on 7/1/2024 and ends on 7/14/2024, my sprint name would be "TeamA sprint 4 7/1-7/14".
I created smart value variables to calculate the sprint start and end dates and I use those variables in the "Send web request" action to create the sprint. The automation works to create the sprint but I can't figure out how to add the date to the sprint name field.
Hello @Jenn Sherman
A variable is stored as text so your attempt to use the date format function on the variable is not going to work.
I recommend you use the same info you are using to set the variable - now.plusDays(14) - with the alternate format.
@Trudy Claspill That worked! I had forgotten about the variable being text. Doing it this way worked. Thanks for the quick response!
{
"originBoardId": "287",
"goal": "",
"name": "YI-G Week {{now.plusDays(14).format("MM/dd")}}-{{now.plusDays(20).format("MM/dd")}} ",
"startDate": "{{now.plusDays(14).jiraDate}}",
"endDate": "{{now.plusDays(20).jiraDate}}"
}
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.