How can I add time time tracking details to my sub tasks on Rapid board

Robert Pepitone
Contributor
August 21, 2012

To make our stand ups more streamlined we'd like to be able to log time on sub tasks directly from our rapid board. How can I add this functionality? All that is currently displayed on the sub task card is summary and priority.

1 answer

1 accepted

0 votes
Answer accepted
sclowes
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 22, 2012

In the 'estimation' tab on the board configuration set the board to use 'Original Time Estimate' for the estimation statistic and 'Time Tracking' on.

Then in the board, if you click on the sub-task the detail view will open. In work mode on the detail view hit the '+' sign next to the remaining estimate lozenge to log work.

Thanks,
Shaun