How can I hide story points on sub-tasks in our kanban board? I can easily remove the field from sub-tasks, but every sub-task card on our kanban board still shows a 0 for story points. It's not the end of the world but it is a little misleading and ugly.
Hi @Benjamin Rosenek ,
Can you confirm that you're looking at kanban and not scrum board? I'm asking as this 'badge' representation of estimation method is not available in kanban boards (as far as I know; see this answer).
As for scrum boards, you can configure estimation/what's displayed by configuring scrum board (Configure board > Estimation > Estimation method).
Additional note, this badge won't be visible in case the estimation field (e.g. Story Points) is empty, but it will still appear if you set the value to 0 (as 0 ≠ none/empty).
Hope this helps.
Cheers,
Tom
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.