Hi all,
I'm working with a company based project.
Setup:
Both Task and Story use the same screen: BC - Default issue screen. Why 'Linked' issues is visible on Task but not on Story? The only way I can think is because in the example below, there is a linked issue to the task, and not on the Story, but then I should at least be able to link an issue..
Story: not visible:
Task; visible:
Hello @Frederik Vanhaelst
When you are viewing a ticket, you can add a linked issue via the "+Add" menu under the summary of the ticket , then select "Linked Issue."
Once you add the first link, a "Linked Issues" line will become visible as your example of a task issue type
Hope this can help
Discover the teamwork and precision behind success on and off the track. See how this high-performing team makes the impossible possible. Be one of the first 100 customers to register for a chance to win 2 tickets to an Atlassian Williams 2026 race.
Register now
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.