How does JIRA Cloud calculates a team's velocity?

Juliano Coimbra
Contributor
May 17, 2018

I have the following number as Sprint Report:

 

Completed:  71

Not Completed: 29

Completed outside the Sprint: 9

Removed from the Sprint: 2

 

And in the Velocity Chart:

Committed: 106

Completed: 71

 

Therefore I only get how the "Completed" is calculated, but I am missing how the "Committed" is.

 

Can someone help me? :-)

 

Thanks in advance!

1 answer

0 votes
Ajay _view26_
Community Champion
May 18, 2018

The Committed includes  all the Issues when you started the Sprint.

It doesnt include issues which were removed or added during the Sprint.

However the numbers doesnt seem to match . Can you post the Sprint Report Table so that the  Issue marked "*" can be counted ?