Hi Friends,

I have moved the one task from project A to Project B. Then  i have tried to close the sprint but it is require the admin permission for Project B. I had admin permission to project A and i have mentioned only  project A in filter too. But it is required the admin permission to Project B. How can i close the sprint without the admin permission of Project B.

Thanks in advance,

Karthik A.

2 answers

1 vote
Ollie Guan
Community Champion
October 22, 2014

Try to query these Issue,and use bulk change to remove the original Sprint ID 

sprint id.jpg

Finally, try to close the sprint

0 votes
David Di Blasio
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
October 23, 2014

Feel free to also watch/vote on the bug we have open for this behavior smile

https://jira.atlassian.com/browse/GHS-9030

Suggest an answer

Log in or Sign up to answer
TAGS
atlassian, likes for trees, atlassian community, social impact, tree planting campaign, community kudos, atlassian giving, environmental impact, sustainability, likes for good, atlassian social responsibility, community challenge

Make every click count—help us plant 50,000 trees! 🌳

Want to make your everyday Community actions directly contribute to reforestation? The Atlassian Community can achieve this goal by liking a post, attending an ACE, sending your peers kudos, and so much more!

Help us plant more trees
AUG Leaders

Atlassian Community Events