How to copy Value from linked issue when status change ?

W September 26, 2024

Hi,

I have the 2 project issue : "Booking" and the linked issue name "Photo"
So I want to set up an automation that : When I change the status of Booking to Revision, the Photo will be copy the custom field X from "Booking" to "Photo" ( Both projects has that field X  )

So could you please help me how to set up the Automation

 

1 answer

1 accepted

0 votes
Answer accepted
Giulia Caberlotto
Contributor
September 26, 2024

Hi, 

If I understood correctly you want to copy the value X from the issue type "booking" to the issue type "photo" when booking is transitioned to the status "revision". 

You'll need to identify which link type you're using and adapt this automation: 

1.png 2.png

The scope would be multiple-project. 

I would say the linked issues match is optional but recommended if you want to limit errors. 

Hope this helps. 

W September 27, 2024

Hi,

Thank you for you help !! I also find out the same way and it works now.
Thanks againnn

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
STANDARD
PERMISSIONS LEVEL
Product Admin
TAGS
atlassian, loom, loom for training, loom for teaching, video training, async learning, online education, screen recording, loom tutorials, loom use cases, atlassian learning, team training tools, instructional video, virtual training tools

🛗 Elevate Your Training and Enablement with Loom

Join us June 26, 11am PT for a webinar with Atlassian Champion Robert Hean & Loom’s Brittany Soinski. Hear tips, stories, and get your burning questions answered. Learn how Loom makes training and enablement easier. Don’t miss it!

Register today
AUG Leaders

Atlassian Community Events