Hello I have the same problem as detailed here:
https://answers.atlassian.com/questions/203455/what-causes-commitment-to-be-zero-on-my-velocity-chart
I commented on that thread but then realised that it is quite old and may not be the best place to ask.
Having got the same problem as detailed detailed in the other question, I think the sprint was not 'started' on time so the start time was retroactivly moved back to when work did start. Now the velocity chart for that sprint looks very odd.
It is something I now know to be careful of in future, but how would I be able to 'fix' it for that sprint?
Regards,
Dan.
I guess based on the Answers you linked to, you should mess around with the dates in relation to the sprint.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.