How to create Milestones in Jira plans. We are managing several Jira Streams in one consolidated Jira Plan.
Hi @Hitesh Bhatt and welcome to the community.
In Jira Plans you can create cross project releases. First you need to create/select releases from each individual project. The cross project release will have an end date of the latest release end date of your selection.
Then you will see blue dots on top of the timeline. One of those is the cross project release which you can highlight.