I am not able to change the status for TO DO to CLOSED
Hi @aetherinno ,
Can you check if a user is having "Transition issues" permission on a specific project?. If a user is having this permission then check if the transition is available from TO DO to CLOSED. If it is not there then you need to add a transition between TO Do to CLOSED status.
Regards,
Kishore Kumar Gangavath.
thanks Kishore ,
can you guide me were to just for transition issues permission on a specific project
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @aetherinno ,
To verify this, You need to be a project admin or JIRA admin or system admin. Then go to Project setting -> Permission scheme in that you will be able to see the "Transition Issues" permission. I have added some screenshots for your reference.
Regards,
Kishore Kumar Gangavath.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
For transition issues permission to enable moving a task from TODO (Open) to Closed, go to Project Settings > Summary > Under Workflows, Press Edit for the Scheme.
In the diagram, you want to set "Done" to "Allow all statuses to transition to this one".
If you can't get to that stage, there is as @[deleted] a permission impediment that is preventing you from editing such project settings.
Hope this helps,
Aaron
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.