I can end a sprint but shows issues as not done

Ravi Mistry
Contributor
March 16, 2017

Hi, 

 

when i am trying to end a sprint the resolution is set to done and closed but when i come to close the sprint i get an error saying it isn't when i have satisfied the workflow in order for it to be completed.

From this - we cannot get a report for end of the sprint. Attached two screenshots below. The

 

Do i need to change a post function once closed or is there something else?

 

Any help or direction into what needs changing will help massively!

 

Thanks, 

 

RaviJIRA_-_Atlassian_issue.png

 

No_sprint_status_report.png

1 answer

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 16, 2017

You need to have your issues in the far right-hand "done" column when you close the sprint - all other columns are "incomplete"

Ravi Mistry
Contributor
March 16, 2017

the screenshot shows the issues all in done column, so we've done this, there are no other issues in other columns.

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 16, 2017

No, it does not.  It shows your issues are in a column named "done", but it's an incomplete column, because it's in the middle of the board. 

Move your incomplete-done column to the done column on the far-right.