I have migrate tasks from one to another and they don't appear in the Roadmap

Xisca Bascuñana
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
March 4, 2022

I created a product as People management but we decided to move all the tasks to a new project that allow us Advanced roadmaps. I moved the tasks but now the tasks don't appear in the roadmap.

How can I make them appear?

 

Thank you all

Xisca

1 answer

1 accepted

2 votes
Answer accepted
Pramodh M
Community Champion
March 4, 2022

@Xisca Bascuñana 

It should be present under Epic where you Source Issues are included as well to be present

Change the Epic Issues for all the tasks for Issues to appear in advanced roadmaps

Thanks,

Pramodh

Xisca Bascuñana
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
March 4, 2022

Thank you Pramodh, you are right, now I'm changing the tasks to epics.

Like Pramodh M likes this