Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Issues in issue count

kA
Contributor
May 2, 2014

Hi Friends,

I have one board, in that board i created the sprint along with 26 issues. But when i tried to complete the sprint it displayed the message in the dialog box like "109 issues were done, 25 incomplete issue will be returened to the backlog". But i have only 26 issues in the sprint. Please refer the attached screen shot.

How it is possible, can you please share your thoughts.

Thanks in advance,

Karthik A.

1 answer

1 accepted

0 votes
Answer accepted
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
May 2, 2014

Check your filters. It's possible to do this by have a filter that covers 134 issues which you draw into your sprint, then you change the filter to show you 26 issues later. When you come to close the sprint, it reports 26 because of the filters, but because there are 134 issues with that sprint, it also wants to tell you about them when you close it.

kA
Contributor
May 5, 2014

Hi Nic,

Thanks for your update.

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events