Jira Scrum board no showing the remaining days in the sprint on top right

Jaithra T James February 26, 2025

I was able to see the remaining days in the sprint for one of the project i created. But now when i created a new project am not able to see the same. Please assist how to add that into the board.

2 answers

1 accepted

0 votes
Answer accepted
Trudy Claspill
Community Champion
February 26, 2025

Hello @Jaithra T James 

Welcome to the Atlassian community.

Can you provide a screen image of the board that does show the days remaining and one that does not, including showing the scheduled end date for the sprint?

What type of project is includes in each board? You can get project type information from the View All Projects page under the Projects menu.

Jaithra T James February 28, 2025

Screenshot 2025-02-28 161432.png

Jaithra T James February 28, 2025

Jira board.pngproject page.png

Jaithra T James February 28, 2025

Hi @Trudy Claspill ,

Thanks for the response,

both the projects are company managed projects.

As am new to Jira, was trying out the features and i came across this issue. could you suggest me. 

I came across a blog i read that it could be possible as 2 project sprints are running parallelly. can you suggest if i need to do any configuration on the board for this. If yes how ?

Trudy Claspill
Community Champion
February 28, 2025

Hello @Jaithra T James 

The two scrum board images you provided appear to be identical. Neither shows days remaining in the sprint.

Can you provide an image that shows a board that shows days remaining in the sprint?

Jaithra T James March 2, 2025

Apologies for the confusion, please find the screenshot that has the days Project V board with days.png

Jaithra T James March 3, 2025

Hi @Trudy Claspill ,

Last day when I updated the screenshot the 'days count' was missing for this same project. Now all of sudden it appeared for a new sprint once I started itEveryday project Days .png

0 votes
Ako Akopov
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 28, 2025

I have the same issue. The number of remaining days was visible on active sprint board but it disappeared and I can't see it now. I have only one active sprint and the project is of company-managed type.

Jaithra T James March 2, 2025

My case it different as some boards have and other doesn't have the days. 